Week 28

One section of parking lot leveled and graveled. Remaining 3 sections being final graded and ready for gravel. South side and rear of building completely closed in. Internal walls for rooms being installed. More heating and AC duct work being installed. North wall frame work complete. 1/3 of roof on the north side complete. Hope to have roof complete by end of next week.