Week 40

Good work week for outside. Building and site work about 3 weeks behind schedule. Final gravel layer being applied to parking lot and driveway. Stucco on building tower completed, rest of building nearing completion. Gutters and down spouts being installed. Air condition system being serviced and checked out. Cabinets installed in sacristy and multi purpose room. Title being installed to walls in restrooms, basin counter tops to be installed next week.